Hudson Meridian was selected by the New York City Economic Development Corporation to manage the construction of this new facility. This fast paced project needed to be completed in 12 months and Hudson Meridian met the challenge bringing the project in on time and on budget. Managing multiple phases and holding multiple GC and MEPS sub-contracts Hudson Meridian was able to masterfully procure, award and execute these contracts based on schedule requirements. After receipt of the Certificate of Occupancy the EVP at the NYCEDC said “extraordinary success, congratulations to all, and thank you.”
Project Highlights:
New 10,000 SF Administration Building with open plan workstations, enclosed offices, kitchen, bathrooms, locker rooms, exercise room and large overhang canopy for vehicle inspections
12.97 acres of vehicle storage including custom designed steel car storage racks to provide storage of over 2,700 vehicles
87,375 cubic foot capacity underground storm water retention system
Sate of the art security system including video surveillance, access control system, bullet proof vehicle redemption area, public address system and perimeter security wall
Project to achieve LEED Silver rating, green building features include: Geothermal heating and cooling system, high albedo roofing membrane, low flow plumbing fixtures, water efficient landscaping, permanent air quality monitoring system and lighting control system
The project required multiple agency approvals
including the following:
NYC Public Design Commission NYC Board Standards and Appeals
NYC Department of Planning NYS DOT
NYS DEC Port Authority of NY & NJ
NYC DEP NYC DOB
All of these agencies had conflicting interests that needed to be satisfied and Hudson Meridian and our Sub-Consultants were able to push the approvals through and still maintain schedule.
|
 |